Contractors
Beware - No-Damage-For-Delay Clauses Enforceable in Indiana
By: Brian M. Falcon, Meyer Najem
Construction, LLC
The Indiana Court of Appeals had
not addressed head-on the enforceability of a no-damage-for-delay clause (“NDD
Clause”) since its decisions in Indiana Dept. of Transp. v. Shelly &
Sands, Inc., 756 N.E.2d 1063 (Ind. Ct. App. 2001) and Stelko Elec. Inc.
vs. Taylor Cmty, Sch. Bldg. Corp., 826 N.E.2d 152 (Ind. Ct. App. 2005). In those
cases, the court enforced the NDD Clauses at issue against contractors seeking
damages on public improvements. While both decisions have since been frequently
relied upon by owners and general contractors seeking to defeat a claim for
delay damages, those decisions were based on projects involving the use and
expenditure of public funds. As such, the decisions, while helpful in
defense, were usually viewed at least in part through that lens. In late 2023,
the Indiana Court of Appeals addressed the NDD Clause once again, this time on
a private project between sophisticated parties on a private construction
project and reached a similar result.
In Luse Thermal Technologies, LLC
v. Graycor Industrial Contractors, Inc., 221 N.E.3d 701 (Ind. Ct. App.
2023), a subcontractor on an industrial project sought damages of $3,667,275.56
for damages resulting in no small part from project delay. The subcontract
included the following variation on a very common NDD clause:
8.8
Delay Claims. The Subcontractor understands and agrees that the potential for
its Work being delayed by the conduct of others is inherent in any construction
project, including the Project. Accordingly, and other than to the extent the
Contractor receives compensation from the Owner or any other entity responsible
for such delay, the Contractor shall not be liable to the Subcontractor for
any damages whatsoever that may be suffered by the Subcontractor, or for
which the Subcontractor may become liable, on account of any acts or
omissions on the part of (a) the Contractor or those for whom it is
responsible, (b) the Owner, (c) the Design Professional, or (d) any
other entity that may arise from or are in any way related to the Project or
the Work. The Subcontractor further agrees: (i) any such delay, other
than to the extent compensation is otherwise provided in this Subcontract,
shall be fully compensated for by an extension of the time to complete
performance of the Work and (ii) it shall make no claim due to delay in the
performance of Work against those who might have a claim against the Contractor
for such damages. (Emphasis added).
Id. at 707.
The
subcontractor attempted to avoid the impact of the NDD clause by characterizing
the damages not as those flowing from delay but instead due to “acceleration”
or “productivity impacts.” Id. at 715-716. Regardless of how the
subcontractor tried to describe its damages, the result was the same and was
driven by the unambiguous language of the NDD Clause. While subcontractors
continue to look for ways to whittle away at a no-damage-for-delay defense,
Indiana’s courts seem unwilling and unmoved to relieve an aggrieved
subcontractor from the bargain it struck, and the contract terms it agreed to
at the outset. Best practice suggests that a sophisticated contractor facing
such a provision either (a) attempt to negotiate the terms and remove or lessen
the impact of the NDD Clause, or (b) price into its contract sum the risks it
is assuming. Otherwise, the contractor is likely to find itself entitled to a
time extension only.