By Joseph
Darr
This article was originally published at Government
Construction Law Update on September 15, 2024. The original post can
be found here: https://www.governmentconstructionlaw.com/
Construction contracts often give one party discretion over
certain aspects of the administration of a project. For example, a contract may
give the owner the “sole discretion” to approve the use of contingency on a job
or whether to give a contractor a time extension for an excusable delay.
Even where an owner has discretion to make specific
determinations under the contract, there is generally at least one legal
principle that limits how the discretion may be exercised—the implied duty of
good faith and fair dealing.
I have written about how a contractor may breach the implied
duty / covenant of good faith and fair dealing (click
here for that post). This post shows how an example of how a public owner
breached the implied duty of good faith and fair dealing by, among other
things, improperly assessing liquidated damages.
The Case
In Appeals
of ECC International, LLC, a contractor was awarded two projects, which
were related to the construction of a military police school for the federal
government. The advertisement for the project in question provided that the
project would have a 365-day period of performance. The contractors bidding on
the project did not know, however, that there were internal communications
among government / owner representatives that the project could not be
completed in 365 days. In fact, one owner representative wrote that the 365-day
period of performance was “NOT POSSIBLE.” Instead, it was thought that the
period of performance should be at least 550-600 days.
During construction of the project, the contractor
encountered numerous issues with the project, which caused the project to be
untimely completed. The owner failed to adjust the completion date for
excusable and compensable delays, and the owner assessed liquidated damages for
late completion of the project. The owner also refused to provide the
contractor with additional compensation that the contractor requested.
Appeal to the Armed Services Board of Contract Appeals
The contractor appealed the owner’s / government’s deemed denial of the
contractor’s various claims. The appeal was with the Armed Services Board of Contract Appeals. The
contractor argued, among other things, that the government breached the duty of
good faith and fair dealing.
The ASBCA outlined the following about the duty of good
faith and fair dealing:
Every contract imposes on each party a duty of good faith
and fair dealing in its performance and enforcement. The covenant of good faith
and fair dealing imposes obligations on both contracting parties that include
the duty not to interfere with the other party’s performance and not to act so
as to destroy the reasonable expectations of the other party regarding the
fruits of the contract. While the implied duty of good faith and fair dealing
cannot expand a party’s contractual duties beyond those in the express contract
or create duties inconsistent with the contract provisions, it prevents a
party’s acts or omissions that, though not proscribed by the contract
expressly, are inconsistent with the contractor’s purpose and deprive the other
party of the contemplated value. The duty to cooperate is an aspect of the
implied duty of good faith and fair dealing.
(Internal quotation marks and citations omitted).
The ASBCA noted that the government imposed a 365-day period
of performance “despite unanimous contemporaneous internal opinion that the
period of performance was far too short and should more appropriately have been
at least 550-600 days.” In other words, the government advertised the project
with a period of performance of 365 days, even though the government knew that
365 days was not likely achievable.
On the other hand, the ASBCA found that the contractor
reasonably believed 365 days would be achievable because the government had
communicated that it was committed to achieving accelerated construction and
the contractor had successfully completed other accelerated projects with the
government. There was also a document provided to the contractor that expressed
the “primary objective is the construction schedule,” and that quality and cost
were secondary objectives.
The Government Fell Short in Three Ways
The ASBCA focused on three shortcomings on the part of the government. First,
the government could have approved “designs that departed from the conceptual
drawings and specifications in ways that were not only compatible with the most
recent guidance, but were also better suited to achieve completion in 365
days.” And the government “chose not to do so.”
Second, the government failed to help the contractor obtain
unfettered access to the job site that would have allowed the contractor to
work double shifts and overtime needed to achieve the schedule. As a result,
the contractor could only work 7.5 hours per day instead of the 20 days per day
it intended to work.
Finally, the ASBCA noted that the government improperly
withheld funds, issued unsatisfactory performance ratings, and assessed
liquidated damages against the contractor. Such actions were improper because,
among other reasons, the government refused to grant relief to the contractor
for government-caused and excusable delays.
The ASBCA concluded that the government breached the
covenant of good faith and fair dealing because the government advertised its
intent to implement an accelerated construction and relaxed design standards
and then administered the contract inconsistent with that advertised intent.
The government’s failure to cooperate with the contractor by implementing the
relaxed design standards and giving the contractor the needed access to job
site deprived the contractor of the contemplated value of the contract. Thus,
the ASBCA held that the contractor was entitled to its damages flowing from the
breach of the implied covenant of good faith and fair dealing.
Bottom Line
Even if an owner has sole discretion as to how to administer a contract,
there are limits on that discretion. In particular, an owner should not
unreasonably exercise any discretion it has under the contract. Otherwise, an
owner may breach the implied covenant of good faith and fair dealing and end up
owing the contractor additional compensation.
Interested in construction claims and want to see more posts
like this one? Follow Joseph Darr on LinkedIn.